Riot Platforms has initiated a large-scale, 1 gigawatt development to expand its Bitcoin mining and hosting capabilities in Navarro County, Texas with its new Corsicana Facility.

Development of the Corsicana Facility has begun with an initial 400 megawatts of capacity on a 265-acre site. The substation was energized in April 2024 and mining operations have begun.
Development 2022 Development Start
2025+ Ongoing Development
Power Capacity Capacity Developed 400 MW
Total Capacity 1 GW
Infrastructure Type 400 MW of Immersion-cooling
Corsicana Hash Rate 15.7 EH/s as of February 28, 2025
Full-Time Employees 165 Local Employees as of February 28, 2024

The Future

Riot’s total self-mining hash rate capacity is expected to reach 36 EH/s by the end of 2024.